Regional housing has a fresh example of how to get a large greenfield site moving. In Wagga Wagga, the planning pieces for a major new community have landed together, and that is the part every developer should take note of.
The Urban Developer reported on 10 November that DevCore and Sunnyside Ventures have been approved to rezone a 350-hectare area in Wagga Wagga's south for 3000 homes. DevCore's share is about 2200 homes in its $2.5 billion Rowan Village project, which The Urban Developer says is delivering more than half of Wagga Wagga's 5000-home target. The key detail is that DevCore secured what the publication called a trifecta: the rezoning planning proposal, development contributions and a development control plan.
Why the trifecta matters
A rezoning on its own is a milestone, not a start date. The land is only truly ready when three things line up: the zoning, a clear contributions framework, and the detailed controls that let a council approve subdivision.
At Rowan Village, those landed close together. According to The Good Builder, Wagga Wagga City Council endorsed finalising the planning proposal for Zone 1 of the Southern Growth Area at its 22 June 2026 meeting, covering roughly 2900 dwellings, and adopted a matching local infrastructure contributions plan at the same time. On 21 September it adopted a development control plan amendment for the Rowan Urban Release Area. Region Riverina reports that the NSW Government published the completed planning instrument in September.
The DCP step is worth understanding. As The Good Builder explains, under the Wagga Wagga Local Environmental Plan the council cannot grant development consent on land within an urban release area until a development control plan has been prepared for that land. With the DCP adopted, that step is cleared, and Committee 4 Wagga reports DevCore was then in a position to submit its Precinct 1 development application for approximately 220 lots.
For a developer, this is the difference between owning zoned land and owning approvable land. Contributions known up front go straight into the feasibility. A DCP in place means the first subdivision application can be lodged without waiting on another planning process.
Patience and partnership with council
None of this happened overnight. Region Riverina reports that councillors unanimously supported the proposal in principle in August 2022. The proposal was then assessed alongside the adjoining Sunnyside development while council worked through infrastructure requirements, environmental studies and planning controls. A revised planning proposal for the wider Zone 1 was exhibited from November to December 2025.
That is a four-year collaboration, and it shows. Running the neighbouring estates together meant infrastructure, contributions and controls could be resolved for the whole growth area rather than site by site.
Infrastructure going in ahead of the homes
The other strength is infrastructure timing. Region Riverina reports that the NSW Government committed about $70.8 million to Wagga Council in 2024 for growth-related works, including the duplication of Plumpton Road and sewer upgrades. Committee 4 Wagga says construction of the Plumpton Road upgrade and the installation of lead-in services to unlock Rowan Village are already under way.
Subject to development approval, DevCore expects construction on Stage One to start in mid-2027, with homes starting to be built in 2028, according to Committee 4 Wagga.
The demand is there
Regional cities need new homes too. Region Riverina notes rental vacancies in Wagga sitting at under one per cent. The Housing Industry Association's Wagga committee chair, Martin Keogh, called Rowan Village "the kind of well-planned, infrastructure supported development Wagga has been waiting for."
What developers can take from it
- Run the planning stack in parallel. Push for the contributions plan and DCP to progress alongside the rezoning, not after it. Each sequential step adds months.
- Partner with neighbours. Where adjoining landholders share a growth area, a joint approach to infrastructure and controls can move the whole precinct faster.
- Lock contributions into the feasibility early. A known contributions plan removes one of the biggest unknowns in a greenfield appraisal.
- Line up infrastructure before the first lot. Roads, sewer and water delivered ahead of housing are what turn a rezoning into titled lots.
- Stage the start. A first precinct of around 220 lots gets the project moving and lets the market set the pace for what follows.
Rowan Village is a good reminder that land supply is unlocked by preparation as much as by policy. When the zoning, contributions and controls line up, and the infrastructure goes in first, a growth area can move from final planning approval to a first subdivision application within weeks.
Sources
- The Urban Developer, Planning Coup Clears the Way for 3000 Homes in Region on the Rise, 10 November 2026: https://www.theurbandeveloper.com/articles/devcore-wagga-wagga-coral-cove-bundaberg-regional-housing-markets-paul-thompson
- Region Riverina, Wagga's $2.5b Rowan Village development poised to deliver 2200 homes after rezoning approval, 21 October 2026: https://regionriverina.com.au/waggas-2-5b-rowan-village-development-poised-to-deliver-2200-homes-after-rezoning-approval/137113/
- The Good Builder, Rowan Village Rezoning Approved for Wagga, With First Homes Due in 2028, 23 October 2026: https://thegoodbuilder.com.au/rowan-village-rezoning-approved-for-wagga-with-first-homes-due-in-2028/
- Committee 4 Wagga, DevCore closer to $2.5b development, 28 October 2026: https://committee4wagga.com.au/news/2026/10/28/devcore-closer-to-25b-development